Overall Project Overview in Real Time as of April 28, 2026

Project Overview

77.1%
1,17,07,353
REMEDIATED (MT)
1,51,86,508
TARGET (MT)

RDF Disposal Status

0.6%
14,288
DISPOSED (MT)
22,77,976
EXPECTED (MT)

Required Performance

3.2%
3,335
TODAY (MT)
1,05,428
REQUIRED TODAY (MT)

Site Reclamation Status

43 Sites
0
100% COMPLETE
2
75–99%
1
50–75%
40
BELOW 50%
Coastline Projects 5 sites 1 cluster
Geron Engineering 5 sites 1 cluster
Iway Associates 3 sites 1 cluster
RaghuRam Hume Pipes 1 site 1 cluster
Saurashtra Enviro 1 site 1 cluster
Sudhakara Infra 1 site 1 cluster
Tharuni Associates 20 sites 1 cluster
Zigma Global 7 sites 1 cluster

Agency Progress

10.5%
25,844
TOTAL REMEDIATED (MT)
2,46,098
TOTAL REQUIRED (MT)

RDF Disposal Status

2.8%
1,033
DISPOSED (MT)
36,914
EXPECTED RDF (MT)

Agency Performance

50.0%
3,335
TODAY (MT)
6,674
REQUIRED (MT)

Site Reclamation Status

5 Sites
0
100% COMPLETE
1
75–99%
1
50–75%
3
BELOW 50%

Outward Performance

3 Sites pending
  • Eluru No outward yet
  • Jaggaihpet No outward yet
  • Jangareddygudem No outward yet

Lagging Sites

  • Eluru 0.0%
  • Jangareddygudem 0.0%
  • Jaggaihpet 0.0%
  • Gudivada 55.6%
  • Machilipatnam 84.8%

Disposal Statistics

12,845 MT
9.9K
SOIL (MT)
1K
RDF (MT)
517
C&D (MT)
1.4K
INERT (MT)

Land Reclaimed

36.7%
59
RECLAIMED (ACRES)
161
TO BE RECLAIMED (ACRES)

Agency Progress

0.6%
656
TOTAL REMEDIATED (MT)
1,16,319
TOTAL REQUIRED (MT)

RDF Disposal Status

0.2%
26
DISPOSED (MT)
17,447
EXPECTED RDF (MT)

Agency Performance

95.2%
3,335
TODAY (MT)
3,504
REQUIRED (MT)

Site Reclamation Status

5 Sites
0
100% COMPLETE
0
75–99%
0
50–75%
5
BELOW 50%

Outward Performance

4 Sites pending
  • Dhone No outward yet
  • Giddalur No outward yet
  • Kavali No outward yet
  • Nandyal No outward yet

Lagging Sites

  • Kavali 0.0%
  • Nandyal 0.0%
  • Dhone 0.0%
  • Giddalur 0.0%
  • Kandukur 1.4%

Disposal Statistics

326 MT
251
SOIL (MT)
26
RDF (MT)
13
C&D (MT)
36
INERT (MT)

Land Reclaimed

32.3%
59
RECLAIMED (ACRES)
184
TO BE RECLAIMED (ACRES)

Agency Progress

38.5%
49,653
TOTAL REMEDIATED (MT)
1,28,919
TOTAL REQUIRED (MT)

RDF Disposal Status

10.3%
1,986
DISPOSED (MT)
19,337
EXPECTED RDF (MT)

Agency Performance

100.0%
2,402
TODAY (MT)
2,402
REQUIRED (MT)

Site Reclamation Status

3 Sites
0
100% COMPLETE
0
75–99%
0
50–75%
3
BELOW 50%

Outward Performance

1 Site pending
  • Mandapet No outward yet

Lagging Sites

  • Mandapet 0.0%
  • Nidadavole 41.1%
  • Tadepalligudem 42.7%

Disposal Statistics

24,678 MT
19K
SOIL (MT)
2K
RDF (MT)
993
C&D (MT)
2.7K
INERT (MT)

Land Reclaimed

38.0%
66
RECLAIMED (ACRES)
176
TO BE RECLAIMED (ACRES)

Agency Progress

0.0%
0
TOTAL REMEDIATED (MT)
15,000
TOTAL REQUIRED (MT)

RDF Disposal Status

0.0%
0
DISPOSED (MT)
2,250
EXPECTED RDF (MT)

Agency Performance

100.0%
454.5
TODAY (MT)
454
REQUIRED (MT)

Site Reclamation Status

1 Sites
0
100% COMPLETE
0
75–99%
0
50–75%
1
BELOW 50%

Outward Performance

1 Site pending
  • kuppam No outward yet

Lagging Sites

  • kuppam 0.0%

Disposal Statistics

0 MT
0
SOIL (MT)
0
RDF (MT)
0
C&D (MT)
0
INERT (MT)

Land Reclaimed

20.4%
12
RECLAIMED (ACRES)
59
TO BE RECLAIMED (ACRES)

Agency Progress

57.8%
4,22,034
TOTAL REMEDIATED (MT)
7,30,367
TOTAL REQUIRED (MT)

RDF Disposal Status

3.0%
3,244
DISPOSED (MT)
1,09,555
EXPECTED RDF (MT)

Agency Performance

35.7%
3,335
TODAY (MT)
9,343
REQUIRED (MT)

Site Reclamation Status

1 Sites
0
100% COMPLETE
0
75–99%
0
50–75%
1
BELOW 50%

Outward Performance

All clear

Every site has outward processing 🎉

Lagging Sites

  • Kurnool 22.0%

Disposal Statistics

40,319 MT
31K
SOIL (MT)
3.2K
RDF (MT)
1.6K
C&D (MT)
4.5K
INERT (MT)

Land Reclaimed

38.8%
9
RECLAIMED (ACRES)
23
TO BE RECLAIMED (ACRES)

Agency Progress

97.0%
90,859
TOTAL REMEDIATED (MT)
93,708
TOTAL REQUIRED (MT)

RDF Disposal Status

10.4%
1,468
DISPOSED (MT)
14,056
EXPECTED RDF (MT)

Agency Performance

100.0%
86.3
TODAY (MT)
86
REQUIRED (MT)

Site Reclamation Status

1 Sites
0
100% COMPLETE
1
75–99%
0
50–75%
0
BELOW 50%

Outward Performance

All clear

Every site has outward processing 🎉

Lagging Sites

  • Tenali 92.8%

Disposal Statistics

18,250 MT
14K
SOIL (MT)
1.5K
RDF (MT)
734
C&D (MT)
2K
INERT (MT)

Land Reclaimed

23.8%
13
RECLAIMED (ACRES)
54
TO BE RECLAIMED (ACRES)

Agency Progress

68.2%
43,59,334
TOTAL REMEDIATED (MT)
63,96,121
TOTAL REQUIRED (MT)

RDF Disposal Status

0.6%
5,892
DISPOSED (MT)
9,59,418
EXPECTED RDF (MT)

Agency Performance

5.4%
3,335
TODAY (MT)
61,720
REQUIRED (MT)

Site Reclamation Status

20 Sites
0
100% COMPLETE
0
75–99%
0
50–75%
20
BELOW 50%

Outward Performance

9 Sites pending
  • Anantapur No outward yet
  • Bapatla No outward yet
  • Narsipatnam No outward yet
  • Palasa-Kasibugga No outward yet
  • Proddatur No outward yet

Lagging Sites

  • Tharuni_Kadiri2 0.0%
  • Tharuni_Adoni 0.0%
  • Tharuni_Yemmiganur 0.0%
  • Proddatur 0.0%
  • Tharuni_Proddatur 0.0%

Disposal Statistics

73,220 MT
56.3K
SOIL (MT)
5.9K
RDF (MT)
2.9K
C&D (MT)
8.1K
INERT (MT)

Land Reclaimed

36.2%
338
RECLAIMED (ACRES)
935
TO BE RECLAIMED (ACRES)

Agency Progress

69.1%
15,64,835
TOTAL REMEDIATED (MT)
22,65,838
TOTAL REQUIRED (MT)

RDF Disposal Status

0.2%
635
DISPOSED (MT)
3,39,875
EXPECTED RDF (MT)

Agency Performance

15.7%
3,335
TODAY (MT)
21,242
REQUIRED (MT)

Site Reclamation Status

7 Sites
0
100% COMPLETE
0
75–99%
0
50–75%
7
BELOW 50%

Outward Performance

6 Sites pending
  • Chittoor No outward yet
  • GVMC No outward yet
  • Guntakal No outward yet
  • Puttur No outward yet
  • Srikalahasti No outward yet

Lagging Sites

  • Sullurpet 0.0%
  • Srikalahasti 0.0%
  • Puttur 0.0%
  • Chittoor 0.0%
  • Guntakal 0.0%

Disposal Statistics

7,898 MT
6.1K
SOIL (MT)
636
RDF (MT)
318
C&D (MT)
874
INERT (MT)

Land Reclaimed

40.0%
100
RECLAIMED (ACRES)
250
TO BE RECLAIMED (ACRES)